| Phase I – 12 months from April 2006 |
Creation of the new slip road and re-configuration of the road network around J21 of M62; construction of the spine road through the site; creation of Plots C, D, E, F, G & H
| Phase II - 12 months from April 2007 |
Creation of the loop road off main spine road to access Plots I, J, K & L
Plot E construction commences
Creation of lagoon to North of Plot T
Plot E completion and first occupiers due October 2007
| Phase III – April 2008 onwards |
Creation of loop road to access Plots M, N, O, P, Q, R, S & T